Today's News

Marshall County Commissioners Split Cost of Conduit with Plymouth

The Marshall County Metronet project is drawing to a close.

The commissioners last week approved a payment agreement between the county and the City of Plymouth for shared conduit installation. The county is to pay half of the cost of the installation and handholds on Lincolnway to State Road 17 on Pioneer Drive, Pioneer Drive to Overmyer Drive and three lateral connections to the three county buildings for a total cost of $37,513.76. The city will pay the same cost for those installation costs.

Continue reading

Marshall County Commissioners Approve Agreement for Meals on Wheels

The Marshall County Commissioners recently discussed a Memorandum of Understanding to continue the Meals on Wheels program at the Marshall County Council on Aging.

County Attorney Jim Clevenger stated that the current agreement expires Dec. 31 of this year and it needed to be renewed. The agreement allows the meals to be cooked at the Marshall County Jail at a cost of $3.25 per person. The personnel at the Marshall County Council on Aging pick up the meals at the jail and deliver them to those in need.

Continue reading

Marshall County Commissioners Hold Public Hearing on Pretty Lake Setbacks

The Marshall County Commissioners held a public hearing during their meeting Monday morning concerning an ordinance regulating building setbacks at Pretty Lake.

Plan Director Ralph Booker explained that the Pretty Lake Homeowners Association approved a change where new construction at the lake would need to be a 45 foot setback from an 789.0 elevation line. The plan commission also approved the ordinance with one commission member against.

Continue reading

Marshall County Commissioners Approve Agreement for Jail Healthcare

The Marshall County Commissioners discussed a contract between the county and Quality Correctional Care, LLC.

Quality Correctional Care, LLC provides the jail’s healthcare needs. The company has provided pharmaceutical needs, a full-time nurse and doctor visits since October of 2013. The current contract expires on Dec. 31 of this year.

County Attorney Jim Clevenger explained that the new contract would be for a four-year term at a cost of $153,000 for the base compensation per year. That figure would not change throughout the duration of the contract. Some add-ons are also available. The monthly cost would be $12,750. A doctor will visit once a week along with a psychologist and a nurse will be there 40 hours a week.

Continue reading

Marshall County Commissioners to Meet Today

The Marshall County Commissioners will meet this morning where a public hearing is scheduled to hear comment on lake set backs in a zoning ordinance amendment. The commissioners will also have a bid opening for farm lease ground.

Marshall County Highway Administrator Laurie Baker will have an update on operations at the highway department and Jim Clevenger will discuss the progress of the jail bonds and a contract with Quality Correctional Care.

Continue reading

Jefferson Street Bridge to Open Today

Jefferson Street bridge

Jefferson Street bridge

The Jefferson Street bridge in Plymouth will open to traffic today.

Marshall County Supervisor of County Highways Jason Peters told WKVI News that the bridge will open at 6:30 a.m. ET. Crews from Beer and Slabaugh will continue to work on the northeast corner of the bridge but traffic will be allowed to pass.

Continue reading

Weather Delays Jefferson Bridge Opening

Jefferson Street bridge

Jefferson Street bridge

It will take a couple of more days to open the Jefferson Street bridge in Plymouth.

Marshall County Supervisor of County Highways Jason Peters told WKVI News that weather has delayed the completion of bridge work. The projected reopening date is now Wednesday.

Bart Trester from USI Consultants told the Marshall County Commissioners last week that the remaining items on the checklist include sidewalks and curbs. Crews also want to reseal the bridge deck to complete the project.

Continue reading

Marshall County Commissioners, Attorney to Review Jail Healthcare Contract

The Marshall County Commissioners and the county attorney will be reviewing the contract with jail’s healthcare service provider when they meet again on Monday, Nov. 17.

Quality Correctional Care sent Sheriff Tom Chamberlin an agreement and it was then forwarded to County Attorney Jim Clevenger for a four year term. The current one-year contract expires on Dec. 31 of this year. The contract calls for a $153,000 contract price which will be good during each of the four years. That price would be reassessed if the county agrees to renew this agreement in 2019, although the county would review services annually.

Continue reading

Marshall County Commissioners Approve Vehicle Purchase for Sheriff’s Department

Marshall County Sheriff Tom Chamberlin requested the purchase of four new vehicles for the department with delivery after the first of the year.

“I would like to get an okay to start ordering the vehicles for delivery. One would be delivered in January and the other three in February. Right now they’re about six weeks out if you start ordering and as Fall comes of course the orders will continue to build and delivery dates will be shoved back. We are hoping to get the vehicles out on the road by April or May. We have to schedule the vehicles with our vendor that puts in all of the equipment,” said Chamberlin.

Continue reading

Three Major Projects in Marshall County on Track for Completion This Year

Jefferson Street bridge

Jefferson Street bridge

Bart Trester from USI Consultants updated the Marshall County Commissioners on a few projects in the county.

Trester said traffic is running on the third phase of the roundabout north of Plymouth on Michigan Road as part of the 7th Road project.

“The contractor is in the process of starting work from the roundabout to the bridge over the Seltenright Ditch in hopes of opening the roundabout this year. Contractors also finished the majority of the bridge construction over Seltenright Ditch with only railing items to be completed,” said Trester.

Continue reading

Marshall County Commissioners to Meet Today

The Marshall County Commissioners will receive updates on three major construction projects when they meet this morning.

Bart Trester from USI will have status updates on the 7th Road construction project, the Metronet project and the Jefferson Street Bridge rehabilitation project.

The commissioners approved paperwork at their last meeting to call sections of the Metronet project substantially complete. Supervisor of County Highways Jason Peters told WKVI News last week that Beer and Slabaugh is working on the east end of the Jefferson Street bridge and that road should be open at the end of next week.

Continue reading

Building Inspector Reports High Permit Purchases in 2014

Marshall County Building Inspector Chuck DeWitt gave the Marshall County Commissioners a quarterly update where he announced the number of permits beginning in August and their permit values.

“We had 35 permits totaling approximately $1.6 million, giving us almost $30 million for the year,” explained DeWitt. “We had 183 inspections during August. In September, we had 52 new permits with a value of $2.4 million which gives us a total of $32 million for the year and 326 permits. We’re probably going to be on track to have about 425 to 440 total permits which is an exceptional year.”

Continue reading

Metronet Project Nearly Finished, Jail Bond Paperwork Finalized

Marshall County Attorney Jim Clevenger told the commissioners this week that the paperwork for the Metronet project is complete.

There were some endorsements and fees that were added to the paperwork that couldn’t be avoided. The conduit installation is nearly finished.

The bonds for the jail project were closed on Wednesday, Oct. 15. The lease amendment was recorded and sent to the state.

Continue reading

Marshall County Highway Department Crews Busy this Summer

The Marshall County Highway Department was busy this summer with the road program.

Supervisor of County Highways Jason Peters told the commissioners Monday morning that crews were able to chip and seal 38 to 40 miles of roads this year.

“We pugged right around five-and-a-half miles, we paved a little over two-and-a-half miles. We used about 2,000 tons of milling for paving. We used about 1,500 ton of that for miscellaneous patching here and there. Roughly 1,000 to 1,500 ton we used for patching which offsets a tremendous amount of money in years to come as far as buying cold mix,” said Peters.

Continue reading

Commissioners Approve and Adopt Road Vacation Ordinance

The Marshall County Commissioners held a public hearing Monday morning concerning the vacation of a portion of 3B Road between Quince and Olive Roads.

Plan Director Ralph Booker explained that the request went before the plan commission at their recent meeting. The members of the plan commission found findings of fact that the conditions have changed in order to defeat the original purpose of the road, there is a public interest to vacate the road and the value of the road will not be diminished with the vacation of the road.

Continue reading

Jefferson Street Bridge Rehabilitation Continues

Jefferson Street bridge

Jefferson Street bridge

The repairs to the Jefferson Street Bridge in Plymouth are on schedule.

Supervisor of County Highways Jason Peters told the Marshall County Commissioners on Monday morning that work is nearly done on the west side of the bridge.

“They’re actually hoping to have that end of the bridge done by Friday. Of course it will be closed for probably a week before that end will all be said and done. Then, they’ll start on the east end. On the east end, they do have the sidewalk off. I think, in previous years, they must have actually cut a hole in the cement and filled it with cement and it actually ran down on the gas line,” Peters said.

Continue reading

Marshall County Commissioners to Meet Today

The Marshall County Commissioners will hold a public hearing on a vacation of part of a road when they meet at 9:30 a.m. ET today.

A portion of roadway on 3B between Olive and Quince is being considered for vacation. A petition has been completed and sent to the landowners for approval by the plan commission. The plan commission drew up an ordinance pertaining to this property which will be up for the public hearing this morning.

Continue reading

Marshall County EMA Director to Apply for Grant Request

Marshall County EMA Director Clyde Avery told the commissioners this week that the county is eligible for the Emergency Management Performance Competitive Grant, but the equipment requested in the grant may not be approved by the state.

Avery explained that he would like to reevaluate the use of the grant if the state will not approve recording equipment that Avery feels is necessary for the Emergency Operations Center.

Continue reading

Marshall County Commissioners Approve 2015 Schedules

The Marshall County Commissioners approved the 2015 pay schedule and the 2015 holiday schedule.

Auditor Penny Lukenbill explained that the year is unique in that there are 27 pays for the year and budgets had to be moved around to accommodate that extra expense. The pay schedule begins Jan. 2.

The holiday schedule was also approved in which the county offices will be closed on Jan. 1, Jan. 19, Apr. 3, May 5, May 25, July 3, Sept. 7, Nov. 3, Nov. 11, Nov 26, Nov. 27, Dec. 24, Dec. 25. Lukenbill stated that the county will follow the state’s holiday schedule.

Marshall County Commissioners Receive Update on Projects

The Marshall County commissioners received an update on the 7th Road project and the Metronet project Monday morning.

USI Consultant’s Bart Trester is the project manager and said the 7th Road project is moving along.

“The contractor has begun the soil stabilization of the sub-grade and should finish from Linden Trail to Seltenright Ditch by the end of the week. This will actually allow them to put in under drains and hopefully begin paving toward the end of the week. They won’t put surface down this year. Traffic has been running on a temporary lane allowing the contractor to construct phase two of the roundabout on Michigan Road. Traffic will be switched to phase three at the end of this week or early next week. They will be running through the center of the roundabout at this time allowing them to construct phase three which is the east side up to Zimmer Ditch,” said Trester.

Continue reading

Click Ad to Visit our Website!
Click to visit our Website!