Knox Board of Works Approves Pay Application For Water Line Project

Knox Board of Public Works
Knox Board of Public Works

The Knox Board of Works this week approved two motions regarding the water line installation project for the Starke County Sheriff’s Department and Detention Center at the intersection of State Road 8 and County Road 550 East in Knox. Bob Alloy with Territorial Engineering approached the board and explained that the work is still taking place for the county’s portion of the project, but the work for the city of Knox has been completed.

Continue reading

Construction Work on the Phoenix House More Than Halfway Done

 
 
The Phoenix House construction project is moving along.

Bob Alloy from Territorial Engineering appeared before the Knox Board of Works members to present a pay application for the construction done. The amount of $82,269 was approved for Chester Construction.

Alloy said about 65 percent of the construction is done. There is $140,000 left to complete the project.

The construction project began in mid-January with site preparations beginning in December. The Phoenix House suffered flooding and grant money was sought by K-IRPC to aid in the construction project. The garage is being expanded to include a storage area, a group meeting room, a library and computer area.